13-J1004-00 NNEG Gas Pipeline Phase II

05 Mar 2018, Admin

     The New NG Metering Station, Natural Gas Pipeline, facilities system is a new unit in the NAVA NAKORN ELECTRICITY GENERATING Company Limited (OWNER) located at 8/8 2nd Floor, Moo2, Muang Nonthaburi Province 11000, Thailand.

      The New NG Metering Station Project has been planned and carried out in order to incorporate and support the increasing of natural gas demands in NNEG Power Plant (SPP).

      The natural gas pipeline is intended to deliver additional Natural Gas from the PTT’s NG Block valve Station to the Facilities Station of new SPP Nava Nakorn Industrial Estate. The gas will serve new SPP and industrial users along the pipeline route.

      New Natural Gas Pipeline will be approximately 3.194 km in length, beginning from the Tie-in point at   PTT’s existing Block Valve Station with Flow rate 50 MMSCFD and ending at the NNEG new facility station in Nava Nakorn Industrial Estate,

     UNITY was selected by OWNER to work as engineering consultant for the Project, Pipeline will be approximately Æ12 inches 3.194 km in length.

      Pipeline will be laid underground from the tie-in point and routed along the allocated ROW selected by Owner to the new SPP NG Metering Station with provision of one spare tie-in - Æ 12 Inches at Tie-In point and spare future Tie-In at new MRS- Æ 10 Inches.

     UNITY is also responsible for PMC services for the New SPP - NG Metering Station.